Release date: 12 April 2002
Promoter – Financial Intermediary
Société Tunisienne de l'Électricité et du Gaz (STEG)Location
Description
The works financed by the Bank will primarily consist of: overhead and underground transmission lines, conventional and metal-clad sub-stations, power transformers, telecontrol and network teletransmission, central control offices, dispatching.
Objectives
The project forms part of STEG's Xth Plan (2002-2006). Its aim is to upgrade and rehabilitate STEG's high-voltage power transmission networks throughout the country and improve their management.
Comments
Electricity
Sector(s)
Proposed EIB finance (Approximate amount)
Some EUR 150million from the Bank's own resources under the EUROMED II Mandate
Total cost (Approximate amount)
Some EUR 525 million
Environmental aspects
The environmental aspects of the project will be analysed with reference to European Directive 97/11.
Procurement
The tender files for the various components of the project will be covered by international competitive bidding with publication in the OJEC.
Status
Signed - 5/07/2002
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).