Release date: 11 December 2001
Promoter – Financial Intermediary
Hrvatska kontrola zracne plovidbe d.o.o. – Croatia Control Ltd. (CCL)Location
Description
The project consists in the upgrading of the Air Traffic Services of Croatia during the period 2002-2004 and includes investment of a new Air Control Centre, new Air traffic Management facilities, and a new telecommunication network.
Objectives
The project aims at improving air safety and has been given highest priority by the Croatian Government.
Comments
Airport.
Sector(s)
Proposed EIB finance (Approximate amount)
Approximately EUR 20 million
Total cost (Approximate amount)
Approximately EUR 41 million
Environmental aspects
The project is not expected to fall under Directive 97/11/EC and no negative impact is foreseen. In fact, improvements in the ATC system will further increase aviation safety and capacity.
Procurement
EIB procedures for international procurement would be applied, where applicable.
Status
Signed - 12/09/2002
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).