    Summary sheet

    Release date
    23 September 2013
    Status
    Reference
    Approved | 12/11/2013
    20120535
    Project name
    Promoter - financial intermediary
    SWIETOKRZYSKIE BRIDGE (FL 2011-0211)
    WOJEWODZTWO SWIETOKRZYSKIE
    Proposed EIB finance (Approximate amount)
    Total cost (Approximate amount)
    PLN 72 million (EUR 17 million)
    PLN 433 million (EUR 104 million)
    Location
    Sector(s)
    Description
    Objectives

    Part financing of the bridge construction over the Wisla (Vistula) river in Polaniec. The project will be allocated under the framework loan for the Region of Swietokrzyskie. The project is co-financed by the Region of Podkarpackie and supported by EC.

    Implementation of the project will enhance transport accessibility of the Swietokrzyskie and Podkarpackie provinces, improving the internal coherence of the region, increasing its economic attractiveness and revitalizing entrepreneurship. The project is located in a Convergence region and is therefore eligible under Article 309(a) "projects for developing less-developed regions" of the EC treaty. The project is expected to benefit from Cohesion Fund finance. The consistency of the project with the Bank policy for lending to the transport sector (Decision CA/452/11) depends on its economic profitability and will be confirmed during appraisal.

    Environmental aspects
    Procurement

    The project falls under Annex II of the Environmental Impact Assessment Directive 2011/92/EU. However the project has been screened in and has been the subject of a full EIA procedure. In addition in 2001 a Strategic Environmental Analysis (SEA) was reportedly carried out. A positive Environmental Decision was issued in November 2011. The project crosses the Vistula River with no piers impeding flow. The impact, on any Natura 2000 areas, and on the environment is to be further appraised.

    The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir 2004/17/EC/ or 2004/18/EC and Dir. 2007/66/EC), with publication of tender notices in the EU Official Journal, as and where appropriate. A tender for the award of construction contract for the bridge was issued on 19 June 2012 in the OJEU (2012/S 115-190048). To be further appraised.

    Related projects
    Link to source

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Documents

    Environmental and Social Data Sheet (ESDS) - SWIETOKRZYSKIE BRIDGE (FL 2011-0211)
    Publication Date
    2 Jan 2014
    Document language
    Main Topic
    Lending
    Document Number
    49040768
    Document Focus
    Environmental Information
    Project Number
    20120535
    Sector(s)
    Regions
    Countries
    Publicly available
    Download now
    Environmental and Social Completion Sheet (ESCS) - SWIETOKRZYSKIE BRIDGE (FL 2011-0211)
    Publication Date
    9 Oct 2017
    Document language
    Main Topic
    Lending
    Document Number
    74436153
    Document Focus
    Environmental Information
    Project Number
    20120535
    Sector(s)
    Regions
    Countries
    Publicly available
    Download now

    General enquiries and comments

    The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
    Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
    Alternatively, the EIB can be contacted through its external offices.
    Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.

    Media enquiries

    Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.

    Complaints mechanism

    Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.

    Zero tolerance against fraud and corruption

    The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.

    Related publications