Summary sheet

Release date
10 January 2012
Status
Reference
Under appraisal | 10/01/2012
20110395
Project name
Promoter - financial intermediary
Expressway R1 (Zarnovica – Sasovske)

Slovak Republic – Ministry of Transport

Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
EUR 38 million
EUR 165 million
Location
Sector(s)
Description
Objectives

The project consists of the construction of a new four-lane section of the expressway R1 between the cities of Zarnovica and Sasovske Podhradie for a total length of 18.047 km with cross section of 22.5 m and design speed of 100 km/h (i.e.: category R22.5/100).

The project will reduce travel time and improve road safety. The expressway alignment has been determined to minimise interferences with the river Hron, the existing railway track of the Slovak Railways and the residential areas of the municipalities concerned. A number of technical and organisational measures aiming at minimising the impacts of the project have been taken in the course of construction and envisaged for the operation phase.

Environmental aspects
Procurement

The current project falls under Annex I of the EIA Directive 85/337/EEC as amended by Directives 97/11/EC and 2003/35/EC, being subject to an assessment in accordance with Articles 5 to 10 of EIA Directive. The whole process for developing the project was completed in September 2008 and its compliance with EIA directives is acceptable for the Bank. The road alignment does not cross any location included in the NATURA 2000 network. The project is expected to generate some 3 Kton of CO2 emissions per year mainly as a result of the induced traffic along the corridor.

The EU Procurement directives (2004/17/EC, 2004/18/EC) have been transposed into Slovak legislation by the Act No. 25/2006 Coll. The main construction contracts for Stage I and Stage II of the project were published in the Official Journal of the European Union (OJEU) under the reference numbers 2007/S 126-154109 and 2008/S 146-196368 respectively. The procurement process is acceptable to the Bank.

Comments

Under Framework Loan.

Link to source

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Documents

Environmental and Social Data Sheet (ESDS) - EXPRESSWAY R1 (ZARNOVICA-SASOVSKE P )
Publication Date
14 May 2016
Document language
Main Topic
Lending
Document Number
66455730
Document Focus
Environmental Information
Project Number
20110395
Sector(s)
Regions
Countries
Publicly available
Download now
Environmental and Social Completion Sheet (ESCS) - EXPRESSWAY R1 (ZARNOVICA-SASOVSKE P )
Publication Date
9 Nov 2016
Document language
Main Topic
Lending
Document Number
70796779
Document Focus
Environmental Information
Project Number
20110395
Sector(s)
Regions
Countries
Publicly available
Download now

General enquiries and comments

The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.

Media enquiries

Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.

Complaints mechanism

Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.

Zero tolerance against fraud and corruption

The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.

Related publications