Link to source
Data sheet
Other links
Summary sheet
Release date
1 October 2003
Status
Reference
Signed | 18/12/2003
20030307
Project name
Promoter - financial intermediary
EDA Power VI
Electricidade dos Açores – EDA SA
Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
Up to 50% of total project cost
Estimated at EUR 145 million
Description
Objectives
Design and implementation of additional electricity generation, transmission and distribution capacity. The investments will be located in all nine of the islands making up the Archipelago of the Açores.
To meet the expected increase in electricity demand through appropriate increases in plant capacity and strengthening of transmission and distribution networks.
Environmental aspects
Procurement
The project falls under Annex II of EC Directive 97/11, which will be complied with in full. The project will have a positive effect on the environment through use of efficient generation plant and enhanced use of renewable energy resources.
Procurement procedures are in compliance with relevant EU directives and national and regional legislation.