    Referenz: 20230065
    Veröffentlichungsdatum: 8 November 2023

    Projektträger – zwischengeschaltetes Finanzinstitut

    A.P. MOLLER CAPITAL P/S,AFRICA FINANCE CORPORATION

    Ort

    Beschreibung

    This operation follows up project 2008-0226 CAPE VERDE WIND POWER PPP. This new project will finance the expansion of promoter's existing windfarm in Santiago island and the installation of at least two Battery Energy Storage Systems (BESS) in Cabo Verde. In detail: i) a 13.5 MW expansion of the Santiago windfarm ii) battery systems (BESS) of approximately 10 MW at Santiago windfarm and of approximately 5MW in the Sal Island.

    Ziele

    As a result of this new project, the renewable energy penetration rate in the two islands will expand, improving the decarbonisation and diversification of the country's energy matrix as well as ensuring a more stable grid system reducing the frequency of blackouts. This will also enable the Government to reach its targets for the sector by 2025. The project is also in line with its NDC and the Electricity Sector Master Plan 2018-2040 which plan to increase the wind power capacity 60 MW by 2030 and contribute to Cape Verde's goal to reduce economy-wide greenhouse gas emissions by 18% by 2030.

    Sektor(en)

    Under Global Europe NDICI guarantee

    Under EFSD+ Guarantee

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 38 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 40 million

    Umweltaspekte

    If the project were located within the EU, the construction of the windfarm extension and the BESS components would usually fall under Annex II of the Environmental Impact Assessment (EIA) Directive 2014/52/EU, amending the EIA Directive 2011/92/EU. The EIB will review the project's potential impacts and avoided CO2 amount at appraisal stage. Construction of 2.6km of transmission line and other grid devices dedicated to the Project are associated facilities and will be included in the review. The project is expected to contribute to climate action and environmental sustainability (CA&ES) objectives, in particular to climate change mitigation.

    Auftragsvergabe

    The promoter has to ensure that implementation of the project will be done in accordance with the EIB's Guide to Procurement (public procurement section).

    Projektstatus

    In Prüfung - 28/08/2023

    Milestone
    In Prüfung

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Kap Verde Energie