Veröffentlichungsdatum: 19 Juni 2019
Projektträger – zwischengeschaltetes Finanzinstitut
VOLTA RIVER AUTHORITYOrt
Beschreibung
The project consists of the rehabilitation and upgrade of the electromechanical equipment and systems of the 160 megawatt (MW) hydropower plant on the Volta river in Ghana.
Ziele
The project will extend the life of existing assets by at least 25 years. It will provide cheap and affordable renewable electricity to the fast growing Ghanaian market.
Sektor(en)
- Energie - Energieversorgung
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 12 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 60 million
Umweltaspekte
If the project was located within the EU, most of its components would fall under Annex II of the Environmental Impact Assessment (EIA) Directive (2014/52/EU), requiring the competent authorities to determine whether an EIA is required. An Environmental and Social Impact Assessment (ESIA) for the project was not required due to the nature of the rehabilitation works that are limited to the replacement of electro mechanical equipment in an existing power plant.
Auftragsvergabe
The project qualifies under public procurement section of the EIB Guide to Procurement 2018. The project is implemented based on a turnkey contract awarded to a reputable international company in October 2013 following a competitive tender. In addition, the promoter hired an international owner's engineer. The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement.
Projektstatus
Unterzeichnet - 30/12/2019
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).