    Referenz: 20180240
    Veröffentlichungsdatum: 24 Januar 2020

    Projektträger – zwischengeschaltetes Finanzinstitut

    STATE ENTERPRISE BORYSPIL INTERNATIONAL AIRPORT

    Ort

    Beschreibung

    The project comprises the delivery of the initial phase of Kyiv Boryspil Airport (KBP) capital investment plan. It consists of a number of infrastructure enhancements at KBP designed to ensure that the highest levels of aviation safety and security are preserved and strengthen its operational resilience. Major works include the rehabilitation of the western airfield system, including the western runway (18R-36L), which has been operating for more than 50 years and is in poor condition, the associated parallel taxiway, the airfield ground lighting and the instrument landing systems, plus a range of other associated airside infrastructure works.

    Ziele

    The project is designed to strengthen the airport's operational resilience and ensure that the highest levels of aviation safety and security are preserved. Major works include the rehabilitation of the western runway (18R-36L), plus a range of other associated airside infrastructure works.

    Kommentar(e)

    This operation is covered by the EU Guarantee for EIB loans outside the EU.

    Sektor(en)

    Garantie im Rahmen des Außenmandats

    This operation is covered by the ELM Guarantee.

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 270 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 351 million

    Umweltaspekte

    If situated in the EU, the new runway construction component would fall under Annex I of the EIA Directive 2011/92/EU requiring a full Environmental Impact Assessment (EIA). The environmental process followed for the individual project components and the compliance with the Bank's environmental and social standards will be assessed during the project appraisal.

    Auftragsvergabe

    The Promoter has to ensure that any procurement procedures are done in accordance with the EIB's Guide to Procurement and the relevant applicable EU public procurement rules.

    Projektstatus

    Unterzeichnet - 12/02/2021

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Ukraine Verkehr