Construction and operation of 7 onshore wind parks for a total capacity of 165 MW in the Austrian Federal State of Lower Austria (municipalities of Bad Deutsch Altenburg-Carnutum, Höflein Ost, Rohrau, Haadfeld, Hof, Seibersdorf and Au). The promoter is an Austrian private company, Energiepark Bruck/Leitha GmbH.
Ziele
The project supports EU and national energy objectives
Kommentar(e)
Sektor(en)
- Energie - Energieversorgung
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 101 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 312 million
Umweltaspekte
All wind farms proposed fall under Annex II of the EIA Directive 2011/92/EU. Therefore they will be subject to an Environmental Impact assessment (EIA) on a case by case basis taking into account the defined criteria set by the competent authority. Furthermore, wind farms have to comply with the EU Habitats 92/43/EEC and the EU Birds Directive 79/409/EEC.
Auftragsvergabe
The promoter is not subject to public procurement procedures as it is neither a public undertaking nor does it enjoy special or exclusive rights in the sense of the EU Procurement Directive 2004/17/EC. Procurement procedures followed will be further appraised.
Projektstatus
Unterzeichnet - 3/05/2013