Veröffentlichungsdatum: 20 Juni 2003
Projektträger – zwischengeschaltetes Finanzinstitut
PLINACRO Ltd (“Plinacro”) – State-owned natural gas transportation and trading companyOrt
Beschreibung
The project involves the extension and modernisation of the Croatian gas transmission system.
Ziele
The extension and modernisation of the Croatian gas transmission system, consisting of:
- a new 180 km trunk pipeline from Zagreb to Slavonski Brod to supply gas to the Slavonia region (Eastern Croatia)
- a new 192 km trunk supply pipeline from Pula (Croatian coast) to Karlovac (near Zagreb) that will connect the existing network to offshore gas fields in the Adriatic sea and further to the Italian gas network (through the existing Northern Adriatic pipeline system )
- a number of dispersed investment schemes for the modernisation/rehabilitation of the existing gas transmission system and implementation of a new network control system - SCADA
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Loan on own resources of up to EUR 95 million
Gesamtkosten (voraussichtlicher Betrag)
Project costs for the 3 elements mentioned above total more than EUR 200 million.
Umweltaspekte
EIA’s are required for gas pipelines in Croatia. Four environmental impact studies are being carried out for the various sections of the new gas pipelines which are still to be completed and reviewed.
Auftragsvergabe
Plinacro will follow EIB’s requirement in respect of international competitive bidding (including a publication in the OJEC).
Projektstatus
Unterzeichnet - 16/12/2003
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).