Summary sheet

Release date
7 July 2025
Status
Reference
Under appraisal | 06/05/2025
20250177
Project name
Promoter - financial intermediary
IPTO DODECANESE INTERCONNECTION
INDEPENDENT POWER TRANSMISSION OPER
Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
EUR 1700 million
EUR 2300 million
Location
Sector(s)
  • Energy - Electricity, gas, steam and air conditioning supply
Description
Objectives

Interconnection of the islands of Kos, Rhodes and Karpathos with the Hellenic Electricity Transmission System. The project consists of two converter stations (Corinth and Kos), two High-Voltage-Direct-Current submarine cables (Corinth to Kos), two Gas-Insulated Switchgear substations (Kos and Karpathos), four submarine cables (Kos to Rhodes, and Rhodes to Karpathos), and an overhead transmission line in Corinth.

The project contributes to the energy and climate policy objectives of the European Union and Greece. It is expected to eliminate the electrical isolation of the concerned islands, ensure a more efficient, reliable and clean electricity supply in comparison to the status quo (local diesel or high-fuel oil power stations), improve security of supply, increase the hosting capacity for connection of Renewable Energy Sources in the region, and contribute to the further economic development of the concerned islands, particularly via tourism.

Environmental aspects
Procurement

The overhead transmission line in Corinth falls under Annex I of the EIA Directive 2011/92/EU as amended by Directive 2014/52/EU. The combined environmental impact assessment for the overhead transmission line in Corinth, the two converter stations (Corinth and Kos), and the two submarine cables (Corinth to Kos) has been submitted to the Ministry of Environment and Energy for approval. The rest of the schemes fall under Category B of Law 4014/2011 and require Standard Environmental Commitments. The submarine cable between Rhodes and Karpathos requires a special ecological assessment in line with Law 4014/2011. All environmental permitting is expected to be obtained during appraisal. The impacts that can be typically expected relate to visual impact, vegetation clearance, collision and electrocution of flying vertebrates, electromagnetic fields, noise nuisance, and disturbances during construction, as well as the possible impacts on protected fauna and flora.

The Bank will require the Promoter to ensure that contracts for implementation of the project have been or will be tendered in accordance with the applicable EU procurement legislation, Directive 2014/25/EU as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.

Milestone
Under appraisal
Link to source

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

General enquiries and comments

The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.

Media enquiries

Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.

Complaints mechanism

Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.

Zero tolerance against fraud and corruption

The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Investigations Division. All reports will be treated as strictly confidential and handled in line with EIB investigation procedures and the EIB Group Anti-Fraud Policy.

Related publications