Project name
Promoter - financial intermediary
Kuopio Energia CHP
Kuopio Energia Ltd.
Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
Up to EUR 60 million.
Up to EUR 135 million.
Description
Objectives
Construction of a new combined heat and power plant unit to replace an older one.
The project will install an advanced peat and biomass-fired technology power plant, which will have a lower environmental impact than the old one it replaces.
Environmental aspects
Procurement
This new CHP power plant is expected to fulfil the criteria for high-efficiency co-generation set up in Directive 2004/8/EC.
The Utilities Directive 2004/17/EC applies to the procurement of the promoter, which is a public undertaking supplying electricity and heat to public networks.