    Reference: SG/E/2024/16
    Received Date: 19 April 2024
    Subject: Corridor Vc Medakovo-Poprikuse
    Complainant: Individual
    Allegations: Negative environmental and social impact of the project
    Type: E - Environmental and social impacts of financed projects/operations
    Admissibility*
    Assessment*
    Investigation*
    Dispute Resolution*
    Consultation*
    Closed*
    30/04/2024
    2/12/2024
    Ongoing

    * Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.

    Case Description

    Summary of the complaint:

    On 19 April 2024, the Complaints Mechanism received a complaint from an individual, concerned about the potential negative environmental and social impacts of the project on the settlement of Močarac. The complainant’s allegations concern 

     

    i. Increased risk of flooding to the complainant’s property 

    ii. Inadequate width of a bypass connecting the settlement of Močarac and the village of Ozimica  

    iii. Increased exposure to dust, pollution, and noise 

    Iv. Lack of engagement and information

    v. Damage to the complainant’s house allegedly caused by construction work related to the project.

     

    Actions of the Complaints Mechanism 

    After conducting an initial assessment of the information available and exchanging views with the promoter and the project stakeholders, the Complaints Mechanism proposes to proceed with a collaborative dispute resolution process, to which the complainant and the promoter have agreed.