    Référence: 20100003
    Date de publication: 10 juillet 2012

    Promoteur – Intermédiaire Financier

    Scottish Hydro Electric Transmission Limited

    Lieu

    Description

    Reinforcement and extension of the high voltage electricity transmission system in Scotland to allow for the connection of renewable generation assets.

    Objectifs

    This is an investment programme aimed at reinforcing and extending the transmission network of the promoter in Scotland, the main purpose being to facilitate the connection and transmission of renewable generation and improve network reliability. The programme comprises 3 transmission line components (approximate aggregate length 550km) and associated substation components comprising new switchgear and additional transformer capacity

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 434 million (GBP 350 million)

    Coût total (montant approximatif)

    EUR 906 million (GBP 731 million)

    Aspects environnementaux

    Considering their technical characteristics, project components fall under either Annex I or Annex II of the EIA Directive. The impacts that can be typically expected for these components relate to visual impact, vegetation clearance, bird strikes and mortality, electromagnetic fields, noise nuisance, disturbance during construction and impact on fauna and flora. Environmental impact studies will be carried out as applicable and mitigating and/or compensation measures applied as necessary.

    Passation des marchés

    The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir 2004/17/EC), with parallel publication of tender notices in the EU Official Journal, as and where appropriate.

    Statut

    Signé - 27/03/2013

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).