    Referenz: 20100003
    Veröffentlichungsdatum: 10 Juli 2012

    Projektträger – zwischengeschaltetes Finanzinstitut

    Scottish Hydro Electric Transmission Limited

    Ort

    Beschreibung

    Reinforcement and extension of the high voltage electricity transmission system in Scotland to allow for the connection of renewable generation assets.

    Ziele

    This is an investment programme aimed at reinforcing and extending the transmission network of the promoter in Scotland, the main purpose being to facilitate the connection and transmission of renewable generation and improve network reliability. The programme comprises 3 transmission line components (approximate aggregate length 550km) and associated substation components comprising new switchgear and additional transformer capacity

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 434 million (GBP 350 million)

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 906 million (GBP 731 million)

    Umweltaspekte

    Considering their technical characteristics, project components fall under either Annex I or Annex II of the EIA Directive. The impacts that can be typically expected for these components relate to visual impact, vegetation clearance, bird strikes and mortality, electromagnetic fields, noise nuisance, disturbance during construction and impact on fauna and flora. Environmental impact studies will be carried out as applicable and mitigating and/or compensation measures applied as necessary.

    Auftragsvergabe

    The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir 2004/17/EC), with parallel publication of tender notices in the EU Official Journal, as and where appropriate.

    Projektstatus

    Unterzeichnet - 27/03/2013

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Vereinigtes Königreich Energie