Date de publication: 9 janvier 2025
Promoteur – Intermédiaire Financier
ORKUVEITA REYKJAVIKURLieu
Description
The project comprises the expansion and refurbishment of existing geothermal power plants and the extension and renovation of the district heating and electricity distribution networks in the Reykjavik area during 2025-2029.
Objectifs
In line with the EU and national energy policies, the project will ensure the security of supply of renewable energy and hot water, as well as will secure and improve the energy efficiency of the corresponding enabling infrastructure. It will also serve the increase in demand for renewable energy and hot water from future housing developments and infrastructure expansion in the Reykjavik area.
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 200 million
Coût total (montant approximatif)
EUR 438 million
Aspects environnementaux
Based on their technical characteristics, the geothermal systems expansion and district heating networks activities fall under Annex II of the Environmental Impact Assessment Directive 2011/92/EU, as amended by Directive 2014/52/EU, which requires the competent national authority to determine the need for an EIA. The electricity distribution activities do not fall under any of the annexes of the Directive. Based on available information at this stage, the environmental impacts of the project are expected to be minor and related mainly to noise, vibration, dust, and traffic disruption, and mostly temporary during the construction, which will be mitigated through appropriate site organisation and construction management. Subsurface risks are expected to be well controlled and managed based on the promoter's extensive experience in the area.
Passation des marchés
As a public undertaking operating in the utility sector of an EEA member state, the Promoter is subject to public procurement and its procurement procedures need to be in line with the relevant applicable EU procurement legislation (Directives 2014/23/EU, 2014/25/EU, where applicable, as well as Directive 92/13/EEC), as transposed in the national legislation, with publication of the tender and award notices in the Official Journal of the European Union, as and where required.
Statut
À l'examen - 19/12/2024
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).