Description

The project will finance the construction of a new high-voltage electrical subsea cable interconnection between Maghtab in Malta and Ragusa in Sicily. The cable will have an approximate length of 122 km, a capacity of 225 MW, and a nominal voltage of 220 kV.

Objectifs

The new cable will operate in parallel with the existing one connected to the same substations in Malta and Italy.

Secteur(s)

  • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

Montant BEI envisagé (montant approximatif)

EUR 171 million

Coût total (montant approximatif)

EUR 300 million

Aspects environnementaux

Given its technical characteristics the project is listed neither under Annex I nor Annex II of the environmental impact assessment (EIA) Directive 2011/92/EU, as amended by Directive 2014/52/EU. The project was however undergone an EIA assessment both in Malta and Italy. In Malta, the EIA was approved in August 2023, and the development permit was issued in January 2024. In Italy, the permitting process began with the submission of the application in August 2023, granting a Construction and Operation permit on 18th December 2024. Screening approval was granted by Regione Sicilia in August 2024, and the public consultation concluded positively in October 2024. Typical impacts that can be expected for the project on both terrestrial and marine environment include habitat damage or loss, noise, chemical pollution, heat and electric field emissions. The most significant impacts that have been identified are during implementation, they are limited and mostly reversible. The permit and the underlying EIA studies confirm that, subject to the implementation of the specified mitigating measures, the project would neither have significant adverse effects on the environment nor adversely affect the integrity of any European site in relation to the site's conservation objectives. The Project is expected to contribute to climate action and environmental sustainability (CA&ES) objectives, in particular to climate mitigation.

Passation des marchés

The promoter shall ensure that contracts for implementation of the Project have been and will be tendered in accordance with the applicable EU procurement legislation, Directive 2014/25/EU as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.

Statut

À l'examen - 5/02/2025

Milestone
À l'examen

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.