    Référence: 20200033
    Date de publication: 19 mai 2020

    Promoteur – Intermédiaire Financier

    ADIF ALTA VELOCIDAD

    Lieu

    Description

    The loan will finance the upgrading of the Navalmoral de la Mata-Plasencia-Cáceres-Mérida-Badajoz railway corridor (about 287 km) to high-speed technical standards, including increase in line speed, electrification and doubling of the existing single track sections.

    Objectifs

    The project, which is part of the high speed rail line Madrid-Extremadura, will improve cross-border connections with Portugal in the Atlantic TEN-T corridor.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 890 million

    Coût total (montant approximatif)

    EUR 1960 million

    Aspects environnementaux

    The project is included in the Spanish Infrastructure, Transport and Housing Master Plan "Plan de Infraestructuras, Transporte y Vivienda PITVI (2012-2024)", for which a Strategic Environmental Assessment was carried out. Screening decisions, Environmental Impact Assessment and developments consents, as well as, conformity with the requirements of the Habitats Directive (92/43/EEC) and Birds Directive (2009/147/EC) will be analysed during the appraisal. The project will promote a modal shift from both road and air to rail and, therefore, it is expected to generate environmental and safety benefits.

    Passation des marchés

    The promoter has to ensure that contracts for implementation of the project have been and will be tendered in accordance with the applicable EU procurement legislation, Directive 2014/25/EU as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.

    Statut

    Signé - 20/11/2020

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Espagne Transports