Référence: 20190112
Date de publication: 18 juillet 2019

Promoteur – Intermédiaire Financier

TENNET HOLDING BV

Lieu

Description

The project comprises the construction of the electricity transmission corridor connecting Borsselle to Rilland, in the south of Netherlands. It includes a new 380kV line from Borssele to Rilland substations, a new 380kV substation at Rilland, extension works at Borssele substation, as well as the works on the 150kV part of the same circuit.

Objectifs

The project will ensure compliance of the transmission network with the Grid Code in Netherlands, and so it will enable the transportation of energy also from onshore and offshore windfarms.

Secteur(s)

  • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

Montant BEI envisagé (montant approximatif)

EUR 250 million

Coût total (montant approximatif)

EUR 509 million

Aspects environnementaux

The 380kV transmission lines and substations of the investments fall under Annex I of the Environmental Impact Assessment (EIA) Directive 2014/52/EU, amending Directive 2011/92/EU, thus requiring an Environmental Impact Assessment, where as other project schemes fall under Annex II of the EIA Directive 2014/52/EU, thus requiring a review by the competent authorities at the planning/consent stage with due regard to the necessity for an Environmental Impact Assessment. According to the available information, one project scheme crosses a Natura 2000 designated site (site code NL3009016, Oosterschelde). The EIA(s) and the Appropriate Assessment(s) have been produced and they will be reviewed during appraisal. The actual impacts, including potential negative impacts on sites of Natura conservation importance, and the planned mitigating and/or compensating measures will be reviewed during appraisal.

Passation des marchés

The EIB will require the promoter to ensure that contracts for the implementation of the project have been tendered in accordance with the relevant applicable EU procurement legislation, Directive 2014/25/EU, where applicable, as well as Directive 92/13/EEC and Directive 89/665/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.

Statut

Signé - 6/03/2020

Clause de non-responsabilité

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The data provided on this page is therefore indicative and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Mots-clés correspondants

Pays-Bas Énergie