    Référence: 20160349
    Date de publication: 15 novembre 2016

    Promoteur – Intermédiaire Financier

    ENERGA SA

    Lieu

    Description

    Hybrid bond for the modernisation and extension of ENERGA's electricity distribution network during the period 2017 - 2019

    Objectifs

    The programme aims to cater for demand growth, reduce losses, connect new end-users as well as renewable generators, and improve the reliability and quality of electricity supply. The programme includes the installation of advanced meters and other smart grid components.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 250 million

    Coût total (montant approximatif)

    EUR 814 million

    Aspects environnementaux

    The programme comprises a large number of electricity distribution schemes up to 110 kV with the majority of schemes being reinforcements of medium and low-voltage equipment and connection of new users with limited environmental impact. Some programme schemes may fall under Annex II of the Environmental Impact Assessment (EIA) Directive 2011/92/EU thus requiring a review by the competent authorities at the planning/consent stage with due regard to the necessity for environmental and biodiversity impact and appropriate assessments. The environmental aspects of the project will be appropriately assessed as part of the Bank's appraisal process.

    Passation des marchés

    The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directives 2004/18/EC, or 2014/24/EU where applicable, and/or 2004/17/EC, or 2014/25/EU where applicable, and/or 2014/23/EU where applicable, as well as Directives 89/665/EEC and 92/13/EEC), as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required.

    Statut

    Signé - 8/09/2017

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Pologne Énergie