    Référence: 20160345
    Date de publication: 24 octobre 2016

    Promoteur – Intermédiaire Financier

    TERNA - RETE ELETTRICA NAZIONALE SPA

    Lieu

    Description

    The proposed project is a multi-component investment programme. The main sub-project concerns the adjustment and renovation of 350 electrical substations recently acquired from the national railway company (RFI). Other sub-projects involve the construction of new substations and the associated connections and the installation of reactive power compensation equipment. The sub-projects of the programme are geographically dispersed throughout Italy.

    Objectifs

    The main purpose of the main sub-project is to enable Terna to take over the operation of the former RFI substations. The main purpose of the other sub-projects is to integrate renewable generation into the grid and to improve quality and reliability of supply.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 200 million

    Coût total (montant approximatif)

    EUR 401 million

    Aspects environnementaux

    Some sub-projects of the programme fall under Annex II of the Environmental Impact Assessment (EIA) Directive. The potential impact of the programme includes visual impact, vegetation clearance, electromagnetic fields, noise nuisance and birds' collision and mortality. Environmental impact studies have been carried out as applicable and mitigating and/or compensation measures will be applied as necessary.

    Passation des marchés

    The Bank will require the promoter to ensure that contracts for the implementation of the programme have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directives 2004/18/EC and/or 2014/25/EC) as interpreted by the Court of Justice of the EU and according to the relevant Italian legislation (D.lgs. 163/2006 and D.lgs. 50/2016).

    Statut

    Signé - 8/12/2016

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).