Description
Widening of a 25.5km section of the A6 motorway between Wiesloch-Rauenberg and Weinsberg (south of Heidelberg, north of Stuttgart) and maintenance of the overall section of 47.1km under a 30-year concession design, build, finance and operate contract (DBFO).
The project includes a 1.3km viaduct which crosses the Neckar Valley.
Objectifs
The main economic benefits will stem from reduced travel times and improved road safety thanks to enhanced road capacity.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 250 million
Coût total (montant approximatif)
Not disclosed.
Aspects environnementaux
The project falls under Annex I of the Environmental Impact Assessment (EIA) Directive 2011/92/EC. Compliance with the Strategic Environmental Assessment (SEA) directive 2001/42/EC, EIA Directive 2011/92/EU, Habitats Directive 92/43/EEC and Birds Directive 79/406/EEC will be reviewed at appraisal.
Passation des marchés
The Bank will require the promoter to ensure that contracts for the implementation of the project are tendered in accordance with the relevant applicable EU procurement legislation (Directive 2004/18/EC and/or 2004/17/EC as well as Directives 89/665/EEC and 92/13/EEC) as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.
Statut
Signé - 20/12/2016
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).