Date de publication: 18 juin 2014
Promoteur – Intermédiaire Financier
MOROCCAN AGENCY FOR SOLAR ENERGYLieu
Description
Construction and operation of a 150 MW concentrating solar power (CSP) Tower plant under the third phase of the Ouarzazate solar power complex.
Objectifs
The project's main objective is to help developing a globally-available, non-carbon power generation technology that ultimately may not require fossil fuel back-up capacity and reduce the costs of CSP for world benefit. By creating a new green industry and increasing the penetration of renewable energy in the country's energy mix, the project will contribute to Morocco's objectives of a more secure energy supply, energy diversification, CO2 emission reductions, increased employment, and protecting the local environment.
Commentaires
This operation is covered by the EU Guarantee for EIB loans outside the EU.
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Garantie au titre du MPE
This operation is covered by the ELM Guarantee.
Montant BEI envisagé (montant approximatif)
EUR 82 million
Coût total (montant approximatif)
EUR 855 million
Aspects environnementaux
If the project were located in the EU, it would fall under Annex II of the Environmental Impact Assessment (EIA) Directive (85/337/EEC) as amended, requiring the competent national authority to determine the need for an EIA. Under Moroccan Law, the project requires a mandatory EIA including initial scoping and public consultation. During appraisal, the Bank will ensure that the project complies with the Bank's principles and standards as regards environmental and social issues.
Passation des marchés
Within the EU, the promoter, being a public contracting authority, would be subject to public procurement procedures according to 2004/17/EU, including publication of contract notices in the Official Journal of the EU. In line with the Bank's principles and its statute, the promoter is following the provisions of the Bank's Guide to Procurement, which includes amongst others international competitive bidding and Official Journal of the EU contract notice publication for the items to be financed by the Bank.
Statut
Signé - 22/12/2014
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).