Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
    Référence: 20130261
    Date de publication: 1 avril 2014

    Promoteur – Intermédiaire Financier

    LIBERIA AIRPORT AUTHORITY

    Lieu

    Description

    The project concerns the urgent rehabilitation of the runway at Roberts International Airport in Monrovia, Liberia, which is in very poor condition and presents a real and ongoing safety risk to aircraft. It also includes improvements to the pavement drainage system, the construction of Runway End Safety Areas (RESAs), the replacement of the runway lighting and the provision of various items of operational and safety related airport equipment. The project will result in a much improved level of compliance with civil aviation international safety standards.

    Objectifs

    Roberts International Airport is a critical transport node for international access to Liberia. Without the project the airport would soon have to be closed, forcing international traffic to fly first to Freetown in Sierra Leone or Abidjan in the Ivory Coast and then either to drive to Liberia or take a connecting regional flight to Spriggs Payne Airport, a small domestic airport located close to Monrovia city centre. This would have a very significant impact on the development of the Liberian economy and on the United Nations Mission in Liberia (UNMIL), which currently numbers about 9,000 personnel plus support and logistics equipment.

    Commentaires

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 22 million

    Coût total (montant approximatif)

    EUR 43 million

    Aspects environnementaux

    All the works required by the project are within the existing airport boundary and no significant environmental impacts are expected. Nonetheless, Liberian environmental law requires a full Environmental and Social Impact Assessment (ESIA) for projects of this type and it is understood that the ESIA will include the emergency airside works being financed under this project as part of the assessment of the impacts of the wider development program. This will be reviewed further during the project appraisal.

    Passation des marchés

    The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement.

    Statut

    Signé - 10/10/2014

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Libéria Transports