Date de publication: 10 décembre 2012
Promoteur – Intermédiaire Financier
GAS NATURAL SDG SALieu
Description
Reinforcement and extension of the electricity distribution network in four Spanish regions (Castilla La mancha, Castilla y León, Galicia - all three convergence regions - and Madrid) during the period 2012-2015.
Objectifs
Reinforcement and extension of the electricity distribution network in four Spanish regions.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 475 million
Coût total (montant approximatif)
EUR 977 million
Aspects environnementaux
Most of the project schemes relate to Medium Voltage (MV) and Low Voltage (LV) and therefore fall under Annex 2 of the EIA Directive 92/2011/EU. Such schemes are expected to have minimal or null environmental impacts.
The project includes also high voltage schemes - lines and substations - that requires an Environmental Impact Assessment following Annex 1 of the EU EIA Directive 92/2011/EU.
Passation des marchés
The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir 2004/18/EC/ or 2004/17/EC and Dir. 2007/66/EC), with publication of tender notices in the EU Official Journal, as and where appropriate.
Statut
Signé - 9/07/2013
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).