Recherche Fr menu ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
    Référence: 20120279
    Date de publication: 11 octobre 2012

    Promoteur – Intermédiaire Financier

    Ministry of Power, Energy and Mineral Resources

    Lieu

    Description

    The project consists of converting four natural gas fired open-cycle power units to a combined cycle mode of operation by the addition of heat recovery boilers and steam turbines (two of the four power plants are to be financed by the EIB). The existing generation capacity of the plants is 470 MW which will increase to 705 MW as a result of the conversions.The conversions will also result in efficiency improvements of 75% and a capacity increase of 50%, without any increase in the amount of fuel used. The plants are located in the Rajshashi and Sylhet regions of Bangladesh.

    Objectifs

    The two project components to be financed by the Bank are eligible under the ALA (Asia and Latin America) general mandate objectives: (a)social and economic infrastructure (energy security, energy infrastructure) and (b) climate change mitigation and adaptation.

    Commentaires

    This operation is covered by the EU Guarantee for EIB loans outside the EU.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Montant BEI envisagé (montant approximatif)

    EUR 82 million

    Coût total (montant approximatif)

    EUR 165 million

    Aspects environnementaux

    If the project components were located in the EU they would fall under Annex II of the EIA directive leaving it up to the competent authority to determine the need for an EIA. The project components are not located near or within areas of nature conservation, and no protected flora and fauna will be adversely affected. No project components will entail permanent physical displacement, however for the associated transmission line components there will be temporary displacement of small businesses and impact on land for crops. The requirement for an EIA, and extent of social assessment required, will be assessed during appraisal.

    Passation des marchés

    The Bank will require the promoter to ensure that contracts funded by the Bank will be implemented in accordance with the Bank's Guide to Procurement.

    Statut

    Signé - 18/11/2013

    Clause de non-responsabilité

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The data provided on this page is therefore indicative and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Mots-clés correspondants

    Bangladesh Énergie