Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
Référence: 20120279
Date de publication: 11 octobre 2012

Promoteur – Intermédiaire Financier

Ministry of Power, Energy and Mineral Resources

Lieu

Description

The project consists of converting four natural gas fired open-cycle power units to a combined cycle mode of operation by the addition of heat recovery boilers and steam turbines (two of the four power plants are to be financed by the EIB). The existing generation capacity of the plants is 470 MW which will increase to 705 MW as a result of the conversions.The conversions will also result in efficiency improvements of 75% and a capacity increase of 50%, without any increase in the amount of fuel used. The plants are located in the Rajshashi and Sylhet regions of Bangladesh.

Objectifs

The two project components to be financed by the Bank are eligible under the ALA (Asia and Latin America) general mandate objectives: (a)social and economic infrastructure (energy security, energy infrastructure) and (b) climate change mitigation and adaptation.

Commentaires

This operation is covered by the EU Guarantee for EIB loans outside the EU.

Secteur(s)

  • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

Montant BEI envisagé (montant approximatif)

EUR 82 million

Coût total (montant approximatif)

EUR 165 million

Aspects environnementaux

If the project components were located in the EU they would fall under Annex II of the EIA directive leaving it up to the competent authority to determine the need for an EIA. The project components are not located near or within areas of nature conservation, and no protected flora and fauna will be adversely affected. No project components will entail permanent physical displacement, however for the associated transmission line components there will be temporary displacement of small businesses and impact on land for crops. The requirement for an EIA, and extent of social assessment required, will be assessed during appraisal.

Passation des marchés

The Bank will require the promoter to ensure that contracts funded by the Bank will be implemented in accordance with the Bank's Guide to Procurement.

Statut

Signé - 18/11/2013

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Bangladesh Énergie