Date de publication: 21 mai 2012
Promoteur – Intermédiaire Financier
ACEA S.p.A.Lieu
Description
Investments to reinforce and extend the electricity distribution network in the Rome metropolitan area
Objectifs
The project will enable the promoter to cater for demand/peak demand growth in specific areas of the network, to reduce losses, and to improve the quality and the reliability of electricity supply.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 100 million
Coût total (montant approximatif)
EUR 255 million
Aspects environnementaux
Current information suggests that the project components could fall under Annex II of the Environmental Impact Assessment Directive (85/337/EEC as amended in 1997 and 2003), requiring the competent authority to determine the need for an EIA in line with the Directive. This will be further assessed during appraisal.
Passation des marchés
The promoter tenders works, supplies and services contracts following procurement rules of relevant national and EU legislation, as defined by Directive 2004/17/EC, including publication in the Official Journal of the EU where appropriate.
Statut
Signé - 25/10/2012
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.