Date de publication: 17 octobre 2013
Promoteur – Intermédiaire Financier
ESKOM HOLDINGS SOC LTDLieu
Description
Implementation and operation of a 100 MW power plant based on an innovative Concentrated Solar thermal Power (CSP) technology. The project will be located in South Africa and benefit from high solar irradiation levels. The promoter is a large state-owned utility. The project will be jointly financed in cooperation with Clean Technology Fund (CTF), IBRD, AfDB, AFD and KfW.
Objectifs
The operation will support the objectives of the South African government to increase the share of renewable energy generation and enhance the efficiency of energy use.
Commentaires
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 75 million
Coût total (montant approximatif)
EUR 856 million
Aspects environnementaux
If the project were located in the EU, it would fall under Annex II of the EIA Directive (85/337/EEC) as amended, requiring the competent national authority to determine the need for an Environmental Impact Assessment (EIA). Under South African Law, the project requires a mandatory EIA including initial scoping and public consultation. During appraisal, the Bank will ensure that the project complies with the Bank's principles and standards as regards environmental and social issues.
Passation des marchés
During appraisal, the Bank will review the procurement procedures and require that they conform to the main mechanisms of Directive 2004/18/EC and the Bank's Guide to Procurement, as amended.
Statut
Signé - 15/05/2014
Clause de non-responsabilité
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The data provided on this page is therefore indicative and cannot be considered to represent official EIB policy (see also the Explanatory notes).