    Référence: 20100562
    Date de publication: 4 février 2011

    Promoteur – Intermédiaire Financier

    ELEKTROPRIVREDA REPUBLIKE SRPSKE AD JP ELEKTROPRIVREDA BOSNE I HERCEGOVINE DD - SARAJEVO JP ELEKTROPRIVREDA HRVATSKE ZAJEDNICE HERCEG-BOSNE DD

    Lieu

    Description

    The project comprises investment schemes in the electricity distribution network in Bosnia and Herzegovina to be implemented between 2012-2016.

    Objectifs

    The project is intended to maintain, modernise and extend the electricity distribution network in Bosnia and Herzegovina. Its purpose is to secure a more stable and reliable supply, to improve the overall service quality, to cater for demand growth and to decrease losses.

    Commentaires

    This operation is covered by the EU Guarantee for EIB loans outside the EU.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Garantie au titre du MPE

    This operation is covered by the ELM Guarantee.

    Montant BEI envisagé (montant approximatif)

    EUR 35 million

    Coût total (montant approximatif)

    EUR 125 million

    Aspects environnementaux

    The EIA Directive 2011/92/EU has been transposed in BIH and EIA processes are already established. The investment schemes come under Annex II of the EIA Directive thus implying a review by the competent authorities. The schemes relate to medium and low voltage reinforcement and expansions, they are expected to have minimal environmental impacts and it is unlikely that they will require an EIA. The Bank's financing will be limited to components that do not necessitate an environmental impact assessment.

    Passation des marchés

    The Promoters are public undertakings and will organise tendering in line with open or restricted procedures, both of which should include a publication in the OJEU.

    Statut

    Signé - 5/06/2014

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).