Référence: 20100418
Date de publication: 29 juin 2012

Promoteur – Intermédiaire Financier

NEDERLANDSE GASUNIE NV

Lieu

Description

The project is part of the promoter's ongoing investment programme to expand the gas transmission infrastructure in the Netherlands, thus strengthening its ability to meet gas demands in Northwest Europe.

Objectifs

The project will expand the gas transmission capacity in the Netherlands to meet demand and flexibility requirements in Northwest Europe. It will thus contribute to the further integration of the European gas market, increased security of supply and providing more transport options for market partcipants. The project schemes meet the criteria of the TEN-energy projects and coincide with a TEN-e priority axis (NG.1). The project is therefore eligible under Article 309 point (c) common interest.

Secteur(s)

Montant BEI envisagé (montant approximatif)

EUR 250 million

Coût total (montant approximatif)

EUR 570 million

Aspects environnementaux

The two project components fall under Annex I of the Environmental Impact Assessment (EIA) Directive 2011/92/EU, thus requiring EIAs. All permits required for the Odiliapeel-Melick section have been received by the promoter. The EIA process for the Wijngaarden-Beverwijk section is expected to be completed in 3Q2012 and all the required permits are expected to be granted by the end of 2012. Typically for this type of investment the impacts are temporary in nature resulting mainly from the construction works.

Passation des marchés

The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir 2004/18/EEC/ or 2004/17/EEC and Dir. 2007/66/EC), with publication of tender notices in the EU Official Journal, as and where appropriate.

Statut

Signé - 19/12/2012

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Pays-Bas Énergie