Référence: 20100173
Date de publication: 1 septembre 2011

Promoteur – Intermédiaire Financier

Hellenic Gas Transmission System Operator (DESFA) S.A.

Lieu

Description

The project consists of extension of national gas transmission system through the construction of some.159 km high pressure pipeline from Aghioi Theodoroi to Megalopolis in Greece. It comprises the installation of two sections of pipeline Aighioi Theodoroi to Examilia (15.6 km) and Examilia to Megalopoli (143.4 km) as well as metering and scraper stations. The project is expected to be implemented until end of March 2013.

Objectifs

The project is introducing natural gas in the Peloponnesus peninsula, which currently is not covered by the natural gas network. The pipeline will supply a new 850 MW CCGT power plant at Megalopolis also bringing gas to the Korinthos, Argos, Nafplio, Tripolis and Megalopolis areas. The installation of the Megalopolis power plant is a key element for the improvement of security of electricity supply in the Peloponnesus. It will guarantee the stability of the electricity network under peak conditions and will allow the gradual decommissioning of the lignite based generation.

Secteur(s)

Montant BEI envisagé (montant approximatif)

EUR 55 million

Coût total (montant approximatif)

EUR 129 million

Aspects environnementaux

The project falls by its technical characteristics under Annex II of the Directive 97/11/EC and amendments. Greek authorities have requested an environmental impact assessment for the project. The EIA study has been submitted in 2010. The approval process is at an advanced stage and expected to be finalised in 2011.

Passation des marchés

The project falls under Directive 2004/17/EC, requiring tender advertisements and notices in the Official Journal of the EU.

Statut

Signé - 30/03/2012

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Grèce Énergie