Date de publication: 12 mai 2010
Promoteur – Intermédiaire Financier
Transelectrica SA
Lieu
Description
The Project aims at reinforcing and upgrading the Romanian electricity transmission network while improving the reliability and quality of electricity supply.
Objectifs
The project contributes to the Bank’s lending priority objectives on convergence regions and security of internal energy supply, by supporting Transelectrica’s medium-term investment programme for modernising and retro-fitting power substations within the power transmission grid.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 65 million.
Coût total (montant approximatif)
EUR 156 million.
Aspects environnementaux
The project consists of eight sub-projects of which seven pertain to the refurbishment and modernisation of existing substations, thus falling under Annex II of the EIA Directive (the remaining concerning the implementation of hardware/software). The National Authority screened the eight sub-projects and did not require an Environmental Impact Assessment. The environmental impact is expected to be minor and essentially limited to the construction phase (e.g. dust emissions, traffic disturbances, noise). The compliance with EU and National Environmental legislation will be analysed during appraisal.
Passation des marchés
The procurement procedures followed and their compliance with the EU Directive on public procurement for entities operating in the energy sector will be investigated during appraisal.
Statut
Signé - 5/08/2010
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).