The project consists in a combined cycle gas turbine (CCGT) power station with an electric capacity of 400 MWe and heating capacity of 240 MWth.
Objectifs
The unit will provide electricity to the grid and heat to the neighbouring towns.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 162 million.
Coût total (montant approximatif)
EUR 400 million.
Aspects environnementaux
Due to its capacity (plant over 300 MWth), the project is subject to the Annex I of the EIA Directive (85/337/EC and amendments) and was required to undergo a full Environmental Impact Assessment. The EIA is completed and the environmental permit was granted by the competent authorities.
Passation des marchés
The main project contractor will be chosen based on Public Procurement Law through negotiations with publication. The procedure will comply with the EU Directive 2004/17/EC.
Statut
Signé - 21/12/2012
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).