    Référence: 20070278
    Date de publication: 13 novembre 2007

    Promoteur – Intermédiaire Financier

    Port Autonome de Marseille (PAM)

    Lieu

    Description

    Fos 2XL project concerns the construction of port infrastructure for two new dedicated container terminals in Fos-sur-Mer, PAM’s western harbour area. The Fos 2XL project is included in France’s long term priority transport infrastructure network.

    Objectifs

    To increase and further develop container shipping activity in the Port of Marseille.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Approx. EUR 100 million

    Coût total (montant approximatif)

    Approx. EUR 200 million

    Aspects environnementaux

    The Project falls under Annex I of the EU Directive 97/11 and requires an EIA. The EIA process has been carried out by the Promoter in two phases, in 2002 for the dredging works and in 2005-2006 for other project works, with corresponding administrative authorizations granted on 8 October 2002 and 10 May 2006, respectively. The appraisal mission will verify that any impacts from the project on internationally/locally protected biodiversity areas have been subject of an appropriate assessment in line with the Habitats Directive, or that the competent authority for nature conservation has determined that this is not required.

    Passation des marchés

    The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2004/17/EEC), with parallel publication of tender notices in the EU Official Journal, as and where appropriate. The status of procurement for the various project components will be reviewed during appraisal.

    Statut

    Signé - 22/10/2008

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    France Transports