Référence: 20070191
Date de publication: 11 octobre 2007

Promoteur – Intermédiaire Financier

Public Power Corporation S. A. (PPC).

 

Lieu

Description

Construction of a new natural gas fired combined cycle power plant (370MW - 420 MW) at Aliveri.

Objectifs

The new plant will replace the existing fuel-oil and lignite fired capacity, reducing thereby pollution, notably CO2 emissions, in relation to the existing plants that will be replaced. It will contribute to cover the demand for electricity in Greece by ensuring that the withdrawn capacity is replaced by the new capacity.

Secteur(s)

Montant BEI envisagé (montant approximatif)

Up to 50% of investment cost

Coût total (montant approximatif)

Under appraisal.

Aspects environnementaux

The project falls under Annex I of EU Directive 97/11/EC, amending 85/337/EEC, which requires a formal Environmental Impact Assessment.

Passation des marchés

The project falls under EU procurement Directive 2004/17/EC.

Statut

Signé - 13/10/2008

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Grèce Énergie