    Référence: 20060238
    Date de publication: 24 novembre 2006

    Promoteur – Intermédiaire Financier

    Antalya Buyuksehir Belediyesi - Antalya Greater Municipality.

    Lieu

    Description

    The project consists of the construction of an 11 km double-track tramway system with 16 stations including a depot, maintenance shops and yards. The project is designed to satisfy passenger demands estimated by the Transportation Master Plan for the year 2020, which is estimated to be up to 14,200 passengers/hour/direction.

    Objectifs

    Transport throughout the municipality of Antalya is currently road-based, comprising public buses, minibuses, taxis and private cars. By developing a rail-based system, the municipality aims to improve the quality and enhance the attractiveness of its public transport services. The main economic benefits of the project are expected to be lower levels of road accidents, travel-time savings, reduction in fuel consumption and vehicle usage costs, and reduction in pollution.

    Commentaires

    Urban Transport.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 60 million.

    Coût total (montant approximatif)

    EUR 122 million.

    Aspects environnementaux

    The Bank’s Environmental Statement 2004 states that “The EIB ensures that all projects it finances […] comply with the EU’s Directive on Environmental Assessment.” Within the EU, the project would be considered to fall within the scope of Annex II of Directive 85/337/EEC (as amended) and it would therefore be for the competent authority to decide whether an EIA was required. During the appraisal, the Bank will therefore investigate the screening process applied to this project and, if an EIA is required, will ensure that environmental studies and public consultation for the project comply with EU Directives.

    Passation des marchés

    The Bank will require the promoter to ensure that implementation of the project will be done in compliance with the Bank’s Guide to Procurement.

    Statut

    Signé - 18/07/2007

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Turquie Transports