    Reference: SG/E/2011/17
    Received Date: 12 December 2011
    Subject: STEG - Sousse Power Plant, Tunisia
    Complainant: Confidential
    Allegations: Inadequate expropriation
    Type: E - Environmental and social impacts of financed projects
    Outcome*: No further reaction from the complainant
    Suggestions for improvement: no
    Admissibility*
    Assessment*
    Investigation*
    Dispute Resolution*
    Consultation*
    Closed*
    12/12/2011
    12/07/2012

    * Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.