Reference: 20080626
Release date: 15 December 2008

Promoter – Financial Intermediary

Enel Distribuzione SpA

Location

Description

The project consists of a 3-year investment programme (2009-2011) aimed at reinforcing and extending the promoter’s distribution electricity networks throughout Italy.

Objectives

The main purpose of the project is to cater for demand growth, to enable connection of new customers and to improve quality and reliability of electricity supply.

Sector(s)

Proposed EIB finance (Approximate amount)

EUR 1000 million.

Total cost (Approximate amount)

EUR 2000-3000 million.

Environmental aspects

All the project schemes will fall under Annex II of the EIA Directive, so leaving to the national competent authority to decide whether an EIA would be required in line with the screening criteria specified in the directive. However, many project schemes are expected to be medium and low voltage reinforcements that will not require formal EIAs and will have minimal or no environmental impact.

The impacts that can be typically expected for the project schemes relate to visual impact, vegetation clearance, impact on flying vertebrates, electromagnetic fields, noise nuisance, and disturbance during construction. The EIA screening criteria applied by the national competent authority in Italy and the provisions for biodiversity assessment of projects will be investigated during appraisal.

Procurement

The promoter is subject to the Public Procurement Act of Italy (Dlgs. 163/06) that came into force in 2006 transposing the EU Directives on public procurement. The promoter’s approach for procurement of goods and services in the distribution sectors will be investigated during appraisal.

Status

Signed - 27/03/2009

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).