    Reference: 20080414
    Release date: 31 October 2008

    Promoter – Financial Intermediary

    RTE EDF Transport S.A.

    Location

    Description

    The project consists of a 4-year investment programme (2008-2011), comprises 31 schemes for reinforcing and extending the promoter’s transmission electricity network throughout France.

    Objectives

    The main purpose of the project is to cater for demand growth while improving efficiency and reliability of supply and to provide for connection of traditional and renewable generation resources.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    Up to EUR 400 million.

    Total cost (Approximate amount)

    EUR 1 149 million.

    Environmental aspects

    Some schemes of the project involving long 400 kV and 225 kV overhead lines will fall under Annex I of the EIA Directive (85/337/EC and amendments), while the remainder will fall under ANNEX II, leaving it to the national competent authority to decide whether an EIA would be required in line with the screening criteria specified in the directive. The impacts that can be typically expected for such project schemes relate to visual impact, vegetation clearance, electromagnetic fields, noise nuisance, and disturbance during construction. The specific requirements of the French environmental legislation and the promoter’s application thereof will be investigated during appraisal. This includes addressing potential negative impacts on sites of nature conservation.

    Procurement

    EIB will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation, including publication of tender notices in the Official Journal of the EU as and where appropriate.

    Status

    Signed - 29/01/2009

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).