    Reference: 20080244
    Release date: 29 July 2008

    Promoter – Financial Intermediary

    Public Establishment of Electricity for Generation and Transmission (PEEGT)

    Location

    Description

    The project involves the construction and operation of a second natural gas fired combined cycle module of 750 MW at Deir Ali power plant.

    Objectives

    The objective is to meet growing electricity demand at a competitive cost, using modern combined-cycle technology, and increase the fuel efficiency of PEEGT power generation park by replacing inefficient oil-fired generation. The project will contribute to the expansion of basic energy infrastructure needed for the economic development of Syria.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    Up to EUR 300 million.

    Total cost (Approximate amount)

    Estimated at some EUR 700 million.

    Environmental aspects

    Due to its size and technical characteristics the project requires an Environmental Impact Assessment (EIA) under EIB guidelines. The EIA process has started and is expected to be finalised in autumn 2008. The project is expected to contribute to meeting growing electricity demand with a lower environmental impact than other fossil fuel based alternatives.

    Procurement

    The project is required to be procured according to the Bank’s Guide to Procurement. The procurement process (international competitive bidding).is ongoing

    Status

    Signed - 8/12/2008

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    Syrian Arab Republic Energy