Release date: 16 March 2009
Promoter – Financial Intermediary
Planta de Regasificación de Sagunto, SA.
Location
Description
Second expansion phase of the Sagunto LNG Plant that will increase the LNG import capacity through the addition of one LNG storage tank and one open-rack seawater vaporiser.
Objectives
The project will increase import capacity of natural gas in line with national energy policy as established by the Spanish Energy Plan for the period 2008-2016 and will contribute to the development of the energy network supplying the European Union. The project is in line with European policy objectives to expand and diversify sources of energy supply.
Sector(s)
Proposed EIB finance (Approximate amount)
Approximately 50% of project cost.
Total cost (Approximate amount)
Approximately EUR 129 million.
Environmental aspects
The proposed expansion was already foreseen at the time of the initial construction of the Sagunto LNG terminal and was included in the EIA that received approval from the Ministry of Environment in November 2002. During its actual planning phase it was screened for potential impacts on the environment by the competent authority in 2007, which decided that an additional environmental impact assessment is not required. The decision was made public in the Boletín Oficial del Estado in 2007.
Procurement
In 2008 a procurement notice was advertised in the EU Official Journal and the national Boletín Oficial del Estado in order to establish a list of pre-qualified contractors for an EPC contract. The tendering procedure is in progress at present.
Status
Signed - 15/02/2010
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).