Release date: 18 March 2005
Promoter – Financial Intermediary
Holding Slovenske Elektrarne d.o.o.
Koprska ulica 92
SI-1000 Ljubljana
Location
Description
The Project involves the construction and operation of two run-the-river hydro power plants of 42.5 MW and 39.5 MW on the river Sava in the east of Slovenia, and a 178 MW pump storage power plant at the Soca river in the west.
Objectives
To contribute to meeting the country’s growing electricity demand while maintaining self-sufficiency and raising the share of renewable energy by exploiting the remaining hydro potential in the country.
Comments
Electricity, gas and water supply.
Sector(s)
Proposed EIB finance (Approximate amount)
Up to EUR 130 million
Total cost (Approximate amount)
Estimated at EUR 260 million
Environmental aspects
For all the project sections, both the Enviromental Impact Assessment and public hearing phase will be completed.
Procurement
The components of the project to be financed by the Bank are open on equal terms to international competition under the principles of transparency, economy and non-discrimination in accordance with the Bank’s procurement criteria.
Status
Signed - 15/02/2006
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).