Construction and operation of a greenfield solar power tower with a 50 MW net power-generating capacity.
Khi Solar One is a 50 MW steam receiver power tower concentrated solar power (CSP) plant with approximately two hours of steam storage and will have an overhead tie-line connection to the grid. The project will be located approximately 15 km south-west of the town of Upington in the Northern Cape province in South Africa.
If the project were located in the EU, it would fall under Annex II of the EIA Directive (85/337/EEC) as amended, requiring the competent national authority to determine the need for an Environmental Impact Assessment (EIA). Under South African Law, the project requires a mandatory EIA including initial scoping and public consultation. During appraisal, the Bank will ensure that the project complies with the Bank's principles and standards as regards environmental and social issues.
The project has followed private procurement rules and the main contractors and suppliers have already been selected. However, the South African power sector is not liberalised and access to the electricity market is only possible through specific tendering procedures. The Bank will appraise the procurement process followed to confirm compliance with the Bank's Guide to Procurement.
This operation is covered by the EU Political Risk Guarantee for EIB loans outside the EU.
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).
Documents
News & Stories
General enquiries and comments
The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.
Media enquiries
Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.
Complaints mechanism
Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.
Zero tolerance against fraud and corruption
The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.
Related publications