Search En menu en ClientConnect
Search
Results
Top 5 search results See all results Advanced search
Top searches
Most visited pages

Signature(s)

Amount
€ 50,000,000
Countries
Sector(s)
Ethiopia : € 50,000,000
Energy : € 50,000,000
Signature date(s)
31/10/2005 : € 50,000,000
Link to source

Summary sheet

Release date
25 April 2005
Status
Reference
Signed | 31/10/2005
20040290
Project name
Promoter - financial intermediary
Gilgel Gibe II Hydropower Plant
Ethiopian Electric Power Corp (EEPCO).
Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
EUR 50 million.
EUR 490 million.
Location
Sector(s)
Description
Objectives

The project consists of a medium-scale Hydro Power plant with a capacity of 428 MW and 385 km of overhead transmission lines and substations. The project is cascaded with the Gilgel Gibe I project, recently commissioned and co-funded by the Bank.

The project aims at increasing power generation capacity in order to satisfy the growing demand in a country where only 15% of the population has access to electricity.

Environmental aspects
Procurement

For the hydropower scheme and transmission component two separate Environmental Impact Assessment have been carried out (in line with provisions of EU Directive 97/11/EC).

The Environmental Management Plans for the overall project propose adequate measures to mitigate negative impacts and relate mainly to guaranteeing water flows in the Gilgel Gibe river, landscaping of disposal areas, as well as of construction sites and roads. Furthermore, special attention will be paid to health education and a health centre will be established. Schemes for resettlement and land and crop compensation have been set up.

Environmental Monitoring structures are available through EEPCO's Environmental unit, with overall supervision by the Government's Environmental Protection Agency (EPA) through reporting.

The scope of the proposed measures adequately covers all identified environmental and social aspects and the overall environmental impact of the project is considered acceptable.

An Engineering, Procurement and Contracting (EPC) contract for the hydropower plant and the related activities was directly negotiated with one of the civil contractors who participated in the Gilgel Gibe I project. The prices are based on the unit prices for the (internationally tendered) contracts of the Gilgel Gibe I project and adjusted for inflation and for technical contingencies. An independent consultant confirmed the appropriate price level of the EPC contract.

The EPC contractor has tendered internationally, with publication in the Official Journal of the European Union, the two subcontracts for the electromechanical and hydro mechanical equipment. The contracts for the transmission lines and substations are also scheduled to be tendered internationally with publication in the OJ. The financing of the Bank will be restricted to those items, for which international tender procedures have been carried out in line with EIB's procurement guide.

Comments

Electricity, Gas and Water Supply.

Link to source

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Photogallery

General enquiries and comments

The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.

Media enquiries

Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.

Complaints mechanism

Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.

Zero tolerance against fraud and corruption

The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.

Related publications