Veröffentlichungsdatum: 17 Juni 2009
Projektträger – zwischengeschaltetes Finanzinstitut
Autoridad Portuaria de Barcelona
Ort
Beschreibung
The project consists of the expansion of the container facilities and improvement of rail and road connections in the port of Barcelona to accommodate future traffic growth.
Ziele
The project is needed to cope with a rapidly increasing traffic serving the Port of Barcelona’s powerful hinterland, covering not only Catalonia but the vast Euro-mediterranean region for which the port has become a main logistic gate.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to EUR 150 million.
Gesamtkosten (voraussichtlicher Betrag)
Approximately EUR 400 million.
Umweltaspekte
The project falls under Annex I of EU EIA Directive, requiring a full EIA. The Project has been the subject of two EIAs, which included environmental impact studies and public consultation. The corresponding environmental authorizations were issued by the Ministerio de Medio Ambiente and published in the Spanish Official Journal on 02/09/98 and 10/07/00. EIA and biodiversity assessment requirements as well as status of environmental mitigation and monitoring for the project will be checked during appraisal.
Auftragsvergabe
The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2004/17/EEC), with parallel publication of tender notices in the EU Official Journal, as and where appropriate.
Projektstatus
Unterzeichnet - 1/12/2009
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).