Veröffentlichungsdatum: 19 Juni 2008
Projektträger – zwischengeschaltetes Finanzinstitut
Bahia de Bizkaia Gas SLOrt
Beschreibung
The project involves the expansion of the existing LNG regasification terminal in the port of Bilbao by a third LNG storage tank (of a size of 150000 m3) and by two vaporisers (sea water).
Ziele
The new installations will form an integral part of the terminal and will raise its regasification capacity by 400000 Nm3/h. The project is in line with European policy objectives to expand and diversify sources of energy supply.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to 50% of project cost.
Gesamtkosten (voraussichtlicher Betrag)
Approximately up to EUR 190 million.
Umweltaspekte
The planned expansion of the terminal was identified by the promoter and the competent authority to classify under Annex II of the EIA Directive 85/337/EEC and its amendments. It was screened for potential impacts on the environment according to stipulations of the directive, and the competent authority decided subsequently that an EIA is not required. The decision was made public in the ‘Boletín Oficial del Estado’ in 9/2007. The existing LNG terminal was subject to an EIA, the approval of which was published in December 2000.
Auftragsvergabe
The promoter informed that a procurement notice was advertised in the EU Official Journal with the objective to establish a list of pre-qualified contractors for an EPC contract. Tendering among the qualified contractors is in progress at present.
Projektstatus
Unterzeichnet - 20/03/2013
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).