    Referenz: 20050392
    Veröffentlichungsdatum: 8 November 2005

    Projektträger – zwischengeschaltetes Finanzinstitut

    A group engaged in the exploration, production, refining and distribution of petroleum products, in the transport and supply of natural gas and in CHP development.

    Ort

    Beschreibung

    The project involves the construction and operation of a natural gas-fired industrial cogeneration plant consisting of two identical gas turbines/steam boiler units (each approximately 40 MWe electricity and 125 t/h steam) to meet the major part of steam demand of a refinery. Surplus electricity will be exported via a new 150 kV overhead line to the national HV-grid.

    Ziele

    Replacement of existing heavy fuel-oil fired power and heat generators to raise the efficiency of the energy conversion, to increase electricity sales to the grid and achieve compliance with the Large Combustion Plant Directive by reducing emissions of SO2, NOx and particulates.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    Estimated at up to 50% of the project cost.

    Gesamtkosten (voraussichtlicher Betrag)

    To be determined.

    Umweltaspekte

    Due to its thermal capacity, the project falls under Annex II of the EIA Directive 85/337/EC. A full EIA has been carried out. The EIA concluded that no site of nature conservation importance (Natura 2000) will be concerned by the project. The project is in line with the European policy objectives of promoting cogeneration, improving the environment and supporting the management and rational use of energy.

    Auftragsvergabe

    Procurement procedures followed the requirements of the European Utilities Directive 93/38/EC and tender notices were published in the OJEU.

    Projektstatus

    Unterzeichnet - 4/12/2006

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Portugal Energie