Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
    Referenz: 20030539
    Veröffentlichungsdatum: 11 August 2004

    Projektträger – zwischengeschaltetes Finanzinstitut

    Idku Natural Gas Liquefaction Company SAE

    Ort

    Beschreibung

    Construction of a second liquefied natural gas terminal at Idku with a design capacity of 3.6 Mt/a. The project is situated next to the first train project on the Idku site currently under construction.

    Ziele

    The plant will enable the export of a part of the proven large natural gas reserves in Egypt and will therefore encourage trade between Egypt and both Europe and the US. It will thus generate substantial foreign exchange revenues for the country.

    Kommentar(e)

    Electricity, Gas and Water Supply.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    Up to USD 350 m.

    Gesamtkosten (voraussichtlicher Betrag)

    Around USD 1,100 m.

    Umweltaspekte

    The Idku LNG production was subject to a full Environmental Impact Assessment due to its size, technical complexity and location (as the case if located within the EU). The EIA was conducted by a reputable international consultant in collaboration with local consultancies and covered also the potential construction of a second train at a later stage considering the site and the facilities to be commonly used by Train-1 and Train-2. The need for a further update of the EIA will be assessed during appraisal.

    Auftragsvergabe

    The project is a private sector type operation with respect to the Bank’s Guide to Procurement. Shareholders are corporates with strong commercial interests in the project. The plant’s production is sold on highly competitive international and European markets.

    Projektstatus

    Unterzeichnet - 5/07/2005

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Ägypten Energie