Date de publication: 20 avril 2012
Promoteur – Intermédiaire Financier
ACS SERVICIOS COMMUNICACIONES Y ENERGIALieu
Description
Construction, operation and maintenance of a concentrated solar power (CSP) plant located in Talarrubias (Badajoz / Extremadura / Spain) with a capacity of 49.9MW and using molten salt storage technology.
Objectifs
The project’s objective is to contribute to the development of renewable energy generation capacity.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 140 million
Coût total (montant approximatif)
EUR 345 million
Aspects environnementaux
The project falls under Annex II of the EIA Directive 85/337/EC (as amended) and has been screened in by the competent national authorities which have required an EIA including public consultation. According to the information available the project grid connection is partly inside a Natura 2000 site, which includes protected bird species. Confirmation will be obtained that the EIA has been carried out in compliance with EU Directives and whether the environmental authority has performed an appropriate assessment in compliance the EU Habitats Directive.
Passation des marchés
Neither the promoter nor the special purpose company are subject to EU Procurement Directives. Suitable procurement procedures, including an appropriate selection of works, goods and services offered at competitive prices should be applied in the project’s best interests. Details will be verified during appraisal.
Statut
Signé - 22/12/2015
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).