Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
    Référence: 20080789
    Date de publication: 28 avril 2010

    Promoteur – Intermédiaire Financier

    GDF Suez

    Lieu

    Description

    The project comprises the development, construction, commissioning and operation of a hydro power plant (Laja, 34.4 MW).

    Objectifs

    The project provides for increasing demand of electricity from renewable energy sources, supporting EU priority objectives related to climate change. The project is in line with ALA mandate by supporting European FDI and promoting environmentally sustainable energy.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    USD 84 million.

    Coût total (montant approximatif)

    USD 112 million.

    Aspects environnementaux

    The project, if located in the EU, would fall under Annex I of the EIA-Directive, requiring an Environmental Impact Assessment (EIA) to be performed including public consultation. The promoter has carried out an EIA and received the environmental authorisation based on this. The details of the EIA, the requirements of Chilean regulations, their compliance to the Bank’s requirements, including public participation and socio-economic assessment, will be examined during the appraisal.

    Passation des marchés

    The procurement of the project is not required to follow public procurement procedures since, under the Bank’s Guide to Procurement, the PPA has been awarded through an open international procedure, which is not considered to have provided any special or exclusive rights to the promoter. Additionally, the Chilean electricity market seems liberalised (to be confirmed at the appraisal). In line with its principles and its statute the Bank will however ensure that contracts for the implementation of the project have followed suitable procurement procedures, ensuring an appropriate selection of works, goods and services offered at competitive prices. Contracts awarded must be negotiated impartially and accord with the project’s best interests.

    Statut

    Signé - 5/05/2011

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Chili Énergie